TTRO (T18199) – Closure of Camp Road 20th July – 23 August 2026
Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure at Upper Heyford, Camp Road
A request has been received from ECL Civil Engineering Ltd for a temporary road closure to apply to a section of Camp Road whilst essential installing 1st leg of rising main to complete S278 works as part of the overall scheme for David Wilson Homes – Heyford Springs works are carried out.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 20 July 2026 up to and including 23 August 2026. This is a 24 hour daily road closure.
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)
Notice of intention to make the Order will be published in the local press.
A copy of the drawing showing the extent of the closure and also the alternative route for traffic is attached.